The Hidden Cost of Poor Communication on a Construction Site

By Calvin Benchimol6 min read

Illustration of an orange envelope between a construction site, office keyboard, money, and charts on a navy background

Most jobsite problems are seen early. What costs money is how long they take to reach the person who can act.

Key takeaways

A rebar crew is tying steel and reaches a spot where material is in the way. They can see they are not getting past it. The foreman gets on the radio and calls it in, and the superintendent actions it right away.

That works. On a busy site, a super hears dozens of calls like it every hour. This post looks at what happens to all the other information supers get: “while I have you,” “by the way,” “can I show you something real quick.” It also looks at the information that never reaches supers at all, and what it costs when they find out too late.

Why does information reach the right person too late?

A superintendent is not short on information. On a big site, dozens of items come through every hour. A worker flags something real, the super means to deal with it, gets pulled elsewhere, and it slips. Nobody wrote it down, so nobody followed up. It comes back later as a blocker.

In our 1141 Bloor case study, we described the same pattern: on a typical site, when a crew is blocked, it can take up to a week for that information to reach the construction manager and get resolved.

What about the small things that go unsaid?

Take a ladder that is not tied off properly. People walk past and notice it. The best outcome is someone ties it off and lets the super know it is handled. That initiative is what every site wants.

More often, the super is busy and a small item does not feel worth raising. Sharing it takes effort today, up and back down the chain: worker to foreman, foreman to super, super to safety coordinator. With everything else going on in a day, it can get lost along the way.

The people who need to know are on site. So are the people who can act. There is just no easy line between them.

An easy line does not magically create a site culture where workers take initiative. That takes a culture where speaking up is valued, appreciated, and recognized, but that is another post: How to Retain Construction Workers.

What does slow information cost?

Assume that risk control works on site, so serious issues are addressed quickly. The costs that are hard to see are idle time, rework, and trades waiting because a floor is not ready. The everyday drag is where the money goes.

The most cited numbers come from a 2018 survey by FMI and PlanGrid of nearly 600 construction leaders. It found that team members spend 5.5 hours a week hunting for project data, and more than 14 hours a week on avoidable issues like rework and conflict resolution. It estimated that poor communication and bad project data account for 48% of rework, about $31.3 billion in the U.S. in 2018. It put the labor cost of fixing mistakes, looking for project data, and managing conflict at $177.5 billion that year.

The survey is a few years old, but the pattern will be familiar to anyone who has run a site.

Where does the money leak?

In the handoffs between trades.

Take window installers. Glazing needs the floor cleared before it can start. Starting a floor before it is ready means demobilizing midway and wasting time. Glazing is paid per unit installed, so a crew that cannot install does not get paid.

If the crew knows ahead of time that floors four and five are clear, they can plan, come in, and work straight through. Planning the clear run ahead of time and communicating the progress to the crew on deck is not trivial when you’re dealing with a complex site.

What does it feel like to find out too late?

Picture the weekly foreman’s meeting. You expected progress from a trade, and it didn’t happen. There is always a good reason, and it takes time to work through them. The super is left with one question: what happened, and what’s the plan now?

Building one whole picture from many parts is part of the job, and it gets harder with scale. By the time the super gets a clear view, the blocker is a delay, and the picture is old news again.

What changes when information moves in time?

On 1141 Bloor Street West, two 40-storey towers started behind. Concrete was already at the 23rd floor when the first precast panel went up, the crane was shared with concrete operations, and the site lost 47 weather days, double what the master schedule allowed.

Crewscope gave the crews clear weekly production goals, a shared view of progress that foremen and project leaders could see, and recognition for work that kept the runway open. Precast installed nine panels a day against a target of seven. Tower 1 precast finished 28 days ahead of schedule, and glazing followed with no demobilization events.

The site superintendent, Guido Mazzone of Deltera, put the wider point this way:

Quote from Guido Mazzone:

Bad jobs force you to carry more contingency because there will be delays.

When what the field sees reaches the right person in time, a blocker becomes something you handle, not something you explain later.

How can information move faster on your site?

Shorten the path between the person who sees it and the person who can act. Crewscope does it by text. A worker ties off the ladder and texts a photo. The AI logs it as resolved with the worker’s name on the record, and lets the safety coordinator know. If it is something the worker cannot fix, the same text goes straight to the right person, and the AI follows up until it is closed. The worker hears back either way. There is no app and no login, and the super does not have to be the relay.

Book a walkthrough to see it on a real site.

FAQs

Why is communication a challenge on construction sites?

Information moves slowly. A superintendent hears a lot of issues in a day, so smaller items can get missed, and by the time an issue reaches the person who can act, it can already be a blocker.

How much does poor communication cost in construction?

A 2018 FMI and PlanGrid survey estimated that poor communication and bad project data account for 48% of rework, about $31.3 billion in the U.S. in 2018. It put the labor cost of fixing mistakes, hunting for project data, and resolving conflicts at $177.5 billion.

What are the hidden costs that do not show up in a daily report?

Idle time, rework, and trades waiting because a floor was not ready. These rarely show up as a line item, but they affect margin, especially in the handoffs between trades.

What is the problem with end-of-day reporting?

It records what happened after the fact. Many jobsite problems are known early in the day. If that information does not reach the right person until the report, the chance to act in time has often passed.

How can you improve communication on a construction site?

Shorten the path from the person who sees an issue to the person who can act. Make it easy to log at the moment it is seen, send it directly to the owner, and follow up until it is closed.

Keep reading

  • Illustrated construction crew in hard hats and safety glasses standing in front of a building under construction

    Leadership & Teams

    How to Retain Construction Workers

    Crews stay where good work gets noticed. Three ways to recognize construction workers on site, from instant notes to monthly meetings.

See Crewscope on your site

Schedule a demo